GDS Q3 FY2026 earnings call

GDS Holdings Limited (GDS) GDS Holdings Limited (GDS) GDS 11/25/2026 Earnings Call GDS Q3 FY2026 earnings call Summary GDS Holdings reported third-quarter 2026 results on November 25, with pro forma revenue up 11.9% year-over-year and adjusted EBITDA up 6.2%,

Illustrative imageIllustrative image

GDS Holdings Limited (GDS)

GDS Holdings Limited (GDS)

GDS

11/25/2026 Earnings Call

GDS Q3 FY2026 earnings call

Summary

GDS Holdings reported third-quarter 2026 results on November 25, with pro forma revenue up 11.9% year-over-year and adjusted EBITDA up 6.2%, as the company remains on track to meet its revised full-year guidance. The pro forma figures adjust for asset monetization and one-time items. Management highlighted robust demand for AI infrastructure in China, noting that year-to-date bookings reached 686 MW and that the company expects to achieve its full-year target of approximately 1 GW. Over 80% of new business comes from the top three internet and cloud customers in China, all contracts are take-or-pay with average move-in periods of 12 months, and the company only targets orders reliant on domestic technologies.

The growth was driven by strong AI-driven demand and GDS's selective approach to new business, focusing on high-quality, low-risk contracts. The company is in the final phase of repricing legacy contracts, which will be largely completed within 18 months. GDS also established one of only two data center REITs listed on the Shanghai Stock Exchange and is at an advanced stage of seeking regulatory approval for its first post-IPO asset injection, expected to complete early next year. These initiatives support the company's strategy to recycle capital and maintain a sound balance sheet.

Operationally, GDS ended the third quarter with a total backlog of 450 MW at the beginning of the year, which is projected to reach 1.15 GW by year-end 2026, assuming 950 MW of new bookings and 250 MW of new billings. Total billings are expected to be 1.4 GW at year-end 2026, and the backlog will be fully billable within two years. The company projects annualized adjusted EBITDA of CNY 6.7 billion in 4Q28, a 21% increase over 4Q26, based solely on contracted business. Net debt is expected to end 2028 at around CNY 38 billion, with the company fully funded to deliver its backlog through a mix of debt and equity.

Management revised its 2026 CapEx guidance down to CNY 8.5 billion from CNY 10 billion, reflecting a small adjustment to the timing of payments to CapEx suppliers, while CapEx incurred during 2026 will be around CNY 12 billion. The company maintains its FY 2026 revenue and adjusted EBITDA guidance unchanged. GDS emphasized its strong balance sheet, with cash and time deposits of approximately CNY 19 billion, and access to low-interest domestic debt and equity markets. The company remains selective about new business and expects utilization rates to dip temporarily into the 70s as new capacity comes online, before trending up to the mid-to-high 80s.

Key risks include potential delays in customer deployments or supply chain disruptions, though management expressed confidence in its domestic supply chain and customer move-in schedules. Opportunities lie in the continued AI infrastructure demand, asset monetization through the C-REIT, and the company's disciplined approach to bookings and financing. Investors will focus on the execution of the backlog, the timing of the C-REIT asset injection, and the company's ability to maintain pricing and yields amid competitive pressures.

Operations Data

Financial Performance

- Pro forma revenue grew 11.9% YoY in 3Q26, adjusting for asset monetization and one-time items.

- Adjusted EBITDA increased 6.2% YoY on a pro forma basis.

- Net debt to last quarter annualized adjusted EBITDA stood at 5.1x at the end of 3Q26.

- Cash plus time deposits were approximately CNY 19 billion, with CNY 4 billion set aside for early redemption of a convertible bond next year.

- Organic CapEx for the first nine months was CNY 4.3 billion; full-year CapEx guidance revised down to CNY 8.5 billion from CNY 10 billion, while CapEx incurred during 2026 will be around CNY 12 billion.

- Operating cash flow was CNY 2 billion for the first nine months, excluding one-time items.

Business/Product Analysis

- Bookings year-to-date reached 686 MW, with a full-year target of approximately 1 GW.

- Over 80% of new business is with the top three internet and cloud customers in China.

- All contracts are take-or-pay with average move-in periods of 12 months.

- Backlog at the beginning of 2026 was 450 MW; projected to reach 1.15 GW by year-end 2026, assuming 950 MW of new bookings and 250 MW of new billings.

- Total billings expected to be 1.4 GW at year-end 2026, and the backlog will be fully billable within two years.

- Annualized adjusted EBITDA projected at CNY 6.7 billion in 4Q28, up 21% from 4Q26, based on contracted business only.

- Net debt projected to end 2028 at around CNY 38 billion, fully funded.

Regional Performance

- New projects are located in a few national hubs where land and power are available, with strong local and central government support.

- The approvals process keeps supply and demand in balance, and GDS consistently obtains approvals for new projects.

Key Metrics

- Utilization rate is at its highest ever level; expected to dip temporarily into the 70s as new capacity comes online, then trend up to the mid-to-high 80s.

- Pricing, development costs, and yields are stable, generating reasonable risk-adjusted returns.

- C-REIT: GDS established one of only two data center REITs listed on the Shanghai Stock Exchange and is at an advanced stage of seeking regulatory approval for the first post-IPO asset injection, expected early next year.

Outlook

Official Company Guidance:

- FY 2026 revenue and adjusted EBITDA guidance maintained unchanged.

- FY 2026 CapEx guidance revised down to CNY 8.5 billion from CNY 10 billion previously, due to a small adjustment to the timing of payments to CapEx suppliers. CapEx incurred during 2026 will be around CNY 12 billion.

- Full-year bookings target of approximately 1 GW for 2026.

- Expects to complete the first post-IPO asset injection into its C-REIT early next year.

Management Qualitative Commentary:

- Management expects the 1.15 GW backlog to be fully billable within two years, driving total billings to over 2.4 GW by end-2028, based solely on contracts signed by end-2026.

- Annualized adjusted EBITDA in 4Q28 is projected at CNY 6.7 billion, a 21% increase over 4Q26, assuming CNY 2.2 million of EBITDA per megawatt for backlog contracts.

- Net debt is expected to end 2028 at around CNY 38 billion, with the company fully funded through a mix of 60% debt and 40% equity.

- Utilization rate is expected to dip temporarily into the 70s as new capacity comes online, then trend up to the mid-to-high 80s.

- The company will remain selective about new business and continue a disciplined approach to bookings and financing.

- No supply chain bottlenecks are anticipated, and customer move-in schedules are expected to remain unchanged.

Q&A Highlights

Q: Yang Liu (Morgan Stanley) – Regarding the CapEx change, is it due to delayed cash payments to suppliers, or also combined with customer indications of a slow delivery schedule or delays in project under construction? A: Dan Newman: It's the first reason – a small adjustment to the timing of payments to our CapEx suppliers. CapEx incurred during 2026 will be around CNY 12 billion, while CapEx paid (investment cash flow) will be CNY 8.5 billion, with the difference being CapEx payables. There is no change to any plans or ongoing execution.

Q: Yang Liu (Morgan Stanley) – Follow-up: Even with current move-in schedule or domestic chipset production schedule, customers have not indicated any delay in product delivery, right? A: Dan Newman: No change at all to any of our plans or ongoing execution.

Q: Sara Wang (UBS) – With steady improvement in utilization rate and more capacity coming online in the next two years, what is the expected range of utilization rate? A: Dan Newman: Utilization rate is at its highest ever level. As new capacity under construction comes into service, utilization will dip back into the 70s, but since everything being built is 100% committed, it's only a transitional dip, and then utilization will trend up into the mid-to-high 80s.

Q: Sara Wang (UBS) – Follow-up: Does that mean customer move-in cadence or ramp-up speed after new product delivery is similar to what we've seen before? A: Dan Newman: Yes. We calculate KPIs based on bringing the entire capacity related to a contract into service, but contracts on average allow for move-in over 12 months. We have not made any change to our assumptions about customer move-in.

Q: Ellie Jiang (Macquarie) – Regarding your outlook for next year's supply, you mentioned limited impact from supply chain bottlenecks. Can you elaborate on the key drivers? Is it because hyperscalers have rich inventory or increasing domestic chip contribution? A: William Huang: In terms of our supply chain, we are very confident there is no bottleneck for us – that's one of the advantages in China. Our assumptions are very careful, based on close communication with customers and tracking their supply chains. All our backlog and delivery schedules will not change. Our bookings fully rely on domestic technologies, so the key bottleneck does not exist for us.

Q: Ellie Jiang (Macquarie) – Follow-up: On the customer side, have hyperscalers indicated they have enough inventory to continue current move-in pace despite external volatilities? A: William Huang: Our assumptions are very careful, based on close communication and tracking of customer supply chains. The delivery schedule for our backlog will not change, and we are confident because our bookings fully rely on domestic technologies.

Transcript

ⓘ Content may contain inaccuracies due to audio quality or AI recognition issues. Please refer to the original audio/video.

Hello, ladies and gentlemen. Thank you for standing by for GDS Holdings Limited's third quarter 2026 earnings conference call. At this time, all participants are in listen-only mode.

After management's prepared remarks, there will be a question-and-answer session. Today's conference call is being recorded. I will now turn the call over to your host, Ms. Laura Chen, Head of Investor Relations for the company.

Please go ahead, Laura.

Thank you. Hello, everyone. Welcome to the third quarter 2026 earnings conference call of GDS Holdings Limited. The company's results were issued via newswire services earlier today and are posted online.

A summary presentation, which we will refer to during this call, can be viewed and downloaded from our IR website at investors.gdsservices.com. Leading today's call is Mr.

William Huang, founder, chairman, and CEO, who will cover the business demand, our bookings, and our capacity position. Mr. Dan Newman, our CFO, will then review the financial results.

Before we continue, please note that today's discussion will contain forward-looking statements made under the safe harbor provisions of the U.S. Private Securities Litigation Reform Act of 1995.

Forward-looking statements involve inherent risks and uncertainties. As such, the company's actual results may be materially different from the views expressed today.

Further information regarding these risks and uncertainties is included in the company's filings with the U.S. SEC. The company does not assume any obligation to update any forward-looking statements, except as required under applicable law.

Please also note that GDS earnings press release and this conference call include discussions of unaudited GAAP financial information, as well as unaudited non-GAAP financial measures.

The press release contains a reconciliation of the unaudited non-GAAP measures to the most directly comparable GAAP measures. I will now turn the call over to Mr. William Huang. Please go ahead, William.

Thank you. Hello, everyone. This is William. Thank you for joining us on today's call. Let's start from the demand side. GDS is 100% focused on providing data center services in the China market. AI in China is developing at a fast pace.

Demand for AI infrastructures is robust. At the beginning of this year, we made the decision to step up our bookings. After the first nine months of 2026, our bookings total 686 MW.

Sales momentum continues, and we expect to achieve our full-year target of around 1 GW. Over 80% of our new business is with the top three internet and the cloud customers in the China market.

These are the highest quality customers who we have been serving for many years. We have been selective about new business. We only target orders which rely on domestic technologies.

All of our contracts are take-or-pay, with move-in periods averaging 12 months. There is no material risk to our disclosed bookings. Our new projects are located in a few national hubs where land and power are available.

There is strong local and central government support for these markets. The approvals process keeps supply and demand in balance. Approvals are given based on proven demand, track record, and financing capability.

We are consistently successful in obtaining approvals for new projects. We do not face any supply chain bottlenecks. As a result, our certainty of delivery is high. We incur CapEx based on customer move-in schedules.

We work closely with our customers to phase our CapEx in sync with their deployments. The economics of our business are stable in terms of pricing, development costs, and yields.

At current pricing level, we are able to generate reasonable risk-adjusted returns.